CAPTION
Approval of Application for Payment No. 2 in the amount of $69,583.42 for the Precinct 1 Build Back Services as submitted by contractor, Servpro of Harlingen/San Benito and as reviewed by the project engineer, Halff Associates.
BACKGROUND
C-18-223-07-31
Fiscal Impact
- CALENDAR YEAR:
- 2018
- ACCT. #:
- 8-1100-429-60-115-092-0-430
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Fiscal impact addressed through PO #786578 including any adjustments necessary.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 12/06/2018 10:54 AM |
| Budget and Management | Veronica Ortiz | 12/06/2018 11:46 AM |
| Final Approval | Monica Salinas | 12/07/2018 05:59 PM |
- Form Started By:
- Erica Espinosa
- Started On:
- 12/03/2018 10:26 AM
- Final Approval Date:
- 12/07/2018