CAPTION
1. Subject to Compliance with HB 1295, requesting approval of Supplemental Agreement No. 1 to the Professional Engineering Services Agreement Contract with Cruz-Hogan Consultants, Inc., due to change and increase in project scope (add sewer lines) for the City of Weslaco Water/Sewer Improvements project.
2. Approval of Work Authorization No. 2 for Cruz –Hogan Consultants, Inc. with an increase of $22,367.00.
2. Approval of Work Authorization No. 2 for Cruz –Hogan Consultants, Inc. with an increase of $22,367.00.
BACKGROUND
Cruz-Hogan Consultants, Inc. was approved on November 20, 2018 (AI-67666). Original contract reflects $30,366.00 the new increase amount is $22,367.00 with a total amount of $53,000.00. See attached Supplemental agreement and Work Authorization No. 2.
Approved as to form
Atlas, Hall & Rodriguez, L.L.P.
By: Stephen L. Crain, Attorney
On: February 6, 2019
| Work Authorization No. 1: | $30,366.00 | |
| Work Authorization No. 2: | $22,367.00 | |
| Total: | $53,000.00 | |
| Available Funds: | $ 5,115.70 | FY 29 (2016) Water/Sewer Improvement funds |
| $270,667.24 | FY 30 (2017) Water/Sewer Improvement funds | |
| $287,703.00 | FY 31 (2018) Water/Sewer Improvement funds | |
| Total Funds: | $563,485.94 |
Approved as to form
Atlas, Hall & Rodriguez, L.L.P.
By: Stephen L. Crain, Attorney
On: February 6, 2019
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 02/06/2019 02:17 PM |
| Final Approval | Monica Salinas | 02/08/2019 05:50 PM |
- Form Started By:
- olerma
- Started On:
- 02/06/2019 01:22 PM
- Final Approval Date:
- 02/08/2019