AI- 68894
Purchasing Department 22.A.4.
CC - REGULAR
Hidalgo County
- Meeting Date:
- 02/12/2019
- Submitted For:
- Marty Salazar
- Submitted By:
- Rocio Villarreal, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Approval for the following change orders in connection with the construction of Hidalgo County Courthouse from contracted vendor, Morganti Texas, Inc.:
1. Null and Void Change Order No. 3
2. Revisions on Change Order No. 5
3. Revisions on Change Order No. 6
4. Change Order No. 7
5. Change Order No. 11
2. Revisions on Change Order No. 5
3. Revisions on Change Order No. 6
4. Change Order No. 7
5. Change Order No. 11
BACKGROUND
1. GMP No. 1 is an amendment and should not be added to the contract through a change order no. 3
2. Revised Change Order No. 5 & 6 to correct contract amount.
2. Revised Change Order No. 5 & 6 to correct contract amount.
Fiscal Impact
- CALENDAR YEAR:
- 2019
- ACCT. #:
- 9-1350-419-40-125-035-0-730
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO 779902Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/08/2019 11:21 AM |
| Budget and Management | Veronica Ortiz | 02/08/2019 01:35 PM |
| Final Approval | Monica Salinas | 02/08/2019 05:50 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 02/08/2019 09:26 AM
- Final Approval Date:
- 02/08/2019