CAPTION

Approval of Change Order #1 from Noble  Texas Builders [with no cost impact] reflecting an extension of the construction days from 106 to 156 days due to delay in County [IT Dept.]  receiving ordered equipment Department in connection with the renovation of the Network Operations Center including authority for County Judge or CC member to execute document. 

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No fiscal impact as CO #1 is solely for extension of construction days.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/18/2019 01:57 PM
Budget and Management Veronica Ortiz 04/18/2019 02:04 PM
Final Approval Monica Salinas 04/18/2019 03:47 PM
Form Started By:
egomez
Started On:
04/17/2019 04:25 PM
Final Approval Date:
04/18/2019