CAPTION
Requesting approval of Change Order No. 1 in connection with the project -"Jackson Drain Improvements", reflecting an increase in the amount of $60,284.51, and additional One Hundred and thrity-three (133) calendar days to contract (No. C-HCDD1-18-048-09-25) with Castle Enterprises, LLC, as recommended by project engineer, Noe Saldivar, P.E., with authority for General Manager, Mr. Raul E. Sesin, P.E., CFM, to execute document, subject to compliance with HB1295.