AI - 77288
6.F.
DD-REGULAR AGENDA SPECIAL MTG
Meeting Date:
09/08/2020
Submitted For:
Raul Sesin
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Requesting approval of  Change Order No. 2  reflecting an increase in the amount of $68,501.00 and twenty (20) additional construction calendar days, in connection with contract No. C-HCDD1-19-074-11-26 -Hidalgo County Drainage District No. 1 "Mission Lateral (Section I) -2018 Bond Referendum project #26" with  Saenz Brothers Construction as recommended by project engineer, Damien B. Tijerina, P.E., L&G Engineering (subject to compliance to HB1295).