AI - 78109
6.B.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 11/03/2020
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 1 reflecting a decrease in the amount of $ -131,548.00, and no additional construction calendar days, in connection with contract No. C-HCDD1-20-042-09-08 -Hidalgo County Drainage District No. 1 project, "Mission Lateral (Section II) -2018 Bond Referendum Project #26" with H & R Lease Service, LLC, as recommended by project engineer, Damien B. Tijerina, P.E., L&G Engineering. (subject to compliance to HB1295)
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 10/30/2020 04:48 PM |
- Form Started By:
- moysalazar
- Started On:
- 10/30/2020 03:11 PM
- Final Approval Date:
- 10/30/2020