AI- 79179
Purchasing Department   11.D.
CC CONSENT AGENDA SPECIAL MTG
Prct. 2
Meeting Date:
01/19/2021
Submitted For:
Eddie Cantu
Submitted By:
Erika Zamora, COMM. PCT. #2
Department:
COMM. PCT. #2

Information

CAPTION

Ratification of the fully executed Change Order No. 3 in connection with Contract No. C-17-324-07-17 and GMP Amendment No. 2 with Erickson Construction, LLC for the Pct 2 Las Milpas Park Youth Facility Project as recommended by project engineer B2Z Engineering, LLC, and subject to compliance with HB1295 when/if applicable.

BACKGROUND

Change Order No. 1 is for additional waterline work, parking lot modifications, weather days, MVEC fee for permanent power, hood system for kitchen exhaust for a total increase in the amount of $33,354.61.
 

Fiscal Impact

CALENDAR YEAR:
2020
ACCT. #:
0-1351-451-22-122-141-0-730
FUNDS AVAILABLE Y/N?:
Y/PENDING
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding pending posting of emergency transfer submitted on 1/15/21.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/15/2021 04:49 PM
Final Approval Monica Salinas 01/15/2021 05:28 PM
Form Started By:
Erika Zamora
Started On:
01/15/2021 11:49 AM
Final Approval Date:
01/15/2021