CAPTION

A. Presentation for discussion, consideration and acceptance of Change Order No 1 for  La Homa Road North Subd  C-CAP-07-009-03-13 for material and work adjustments in the amount of $7,373.00 (decrease) project engineer is R. Gutierrez Engineering Corporation, and contractor is JM Construction, a Border Colonia Access Program Project(s).
B. Requesting approval of  Certificate of Construction Completion  submitted by project engineer Javier Hinojosa Engineering reflecting the completion date of March 13, 2007 for La Homa Road North Subdivision with contractor Juan Mendoza Corporation dba J.M. Construction. C-CAP-07-009-03-13

BACKGROUND


Fiscal Impact

FISCAL YEAR:
ACCT. #:
8-1311-431-00-123-384-1-733/734
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Agenda item requires no funding. Change Order No.1 will reduce the initial funding allocation by the remaining account balance of $7,373.00.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/14/2008 03:13 PM
Budget and Management Dina Trevino 02/14/2008 03:37 PM
Rey Salazar Rey Salazar 02/15/2008 09:44 AM
Auditor's Office 02/15/2008 06:44 PM
Form Started By:
lmoya
Started On:
02/13/2008 03:29 PM
Final Approval Date:
02/15/2008