CAPTION
1. Public Hearing regarding a Substantial Budget & Program Amendment to the Hidalgo County Urban County Program’s Annual Action Plan for Program Year 33 (2020) to include the COVID-19 CDBG-CV 3 funding.
2. Requesting approval of and for submission of the Substantial Budget & Program Amendment to the Hidalgo County Urban County Program’s Annual Action Plan for Program Year 33 (2020) to include the COVID-19 CDBG-CV 3 funding.
3. Authorization for County Judge Richard F. Cortez to sign any and all documents related to COVID 19 CDBG-CD 3 funding.
2. Requesting approval of and for submission of the Substantial Budget & Program Amendment to the Hidalgo County Urban County Program’s Annual Action Plan for Program Year 33 (2020) to include the COVID-19 CDBG-CV 3 funding.
3. Authorization for County Judge Richard F. Cortez to sign any and all documents related to COVID 19 CDBG-CD 3 funding.
BACKGROUND
FUNDS AVAILABLE
COVID-19 CBCV 3 FUNDS:
COVID-19 CBCV 3 FUNDS:
CDBG-CV3: $3,322,168.00
The Project lines items being amended are as follow:
A draft copy of the Substantial Amendment for the 2020 Annual Action Plan (CDBG-CV 3) was made available for public review at the Urban County Program office, Hidalgo County Precinct offices and the county website for a five (5) day comment period beginning on April 5, 2021 and ending on April 9, 2021. All comments received will be noted in the final COVID-19 Substantial Amendment to the 2020 Annual Action Plan (CDBG-CV 3) submitted to HUD.
The Project lines items being amended are as follow:
| Existing Budget | FY & Activity | Proposed Budget | Proposed Budget |
| $3,000,000.00 | CDBG-CV- PF-HEALTH FACILITY | $2,200,000.00 | Construct a testing and diagnosis facility to include but not limited to a laboratory in a clinical setting with its own HVAC system which will prevent and respond to the spread of infectious diseases such as the Coronavirus disease 2019 (COVID-19). To include but not limited to offsite and onsite infrastructure improvements for facility operations and special storage area for equipment and supplies. |
| $1,500,000.00 | CDBG-CV PUBLIC SERVICE (GENERAL) | $1,000,000.00 | Project includes the purchase of furniture, fixtures and equipment for the overall operations of the Health Facility. |
| $59,466.00 | CDBG-CV-GENERAL ADMINISTRATION | $ 122,168.00 | Funds shall be used for expenses related to compliance with CDBG-CV requirements including but not limited to advertisements, postings and coordinating project activities and related eligible activities for CDBG-CV funds. |
| $4,559,446.00 | $3,322,168.00 | TOTAL ADDITIONAL CDBG-CV 3 FUNDS |
A draft copy of the Substantial Amendment for the 2020 Annual Action Plan (CDBG-CV 3) was made available for public review at the Urban County Program office, Hidalgo County Precinct offices and the county website for a five (5) day comment period beginning on April 5, 2021 and ending on April 9, 2021. All comments received will be noted in the final COVID-19 Substantial Amendment to the 2020 Annual Action Plan (CDBG-CV 3) submitted to HUD.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 04/06/2021 10:40 AM |
| Final Approval | Monica Salinas | 04/09/2021 06:10 PM |
- Form Started By:
- mmeza
- Started On:
- 04/01/2021 03:13 PM
- Final Approval Date:
- 04/09/2021