AI - 80445
2.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/20/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 3 reflecting a net increase of $46,162.60, and seventy-two (72) additional construction calendar days, in connection with Contract C-HCDD1-20-042-09-08 -"Mission Lateral Section II -2018 Bond Referendum Project #26" with H&R Lease Service, LLC, as recommended by Project Engineer, L&G Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/16/2021 03:52 PM |
- Form Started By:
- moysalazar
- Started On:
- 04/15/2021 03:05 PM
- Final Approval Date:
- 04/16/2021