CAPTION

Requesting approval of  Change Order No. 1  reflecting an increase in the amount of $75,685.52, and one hundred ninety (190) additional construction calendar days, in connection with contract No. C-HCDD1-20-034-08-11 -Hidalgo County Drainage District No. 1 "Jackson Rd. Drain Phase I -2018 Bond Referendum project #16" with  RG Enterprises, LLC dba G&G Contractors, as recommended by project engineer, Quintanilla, Headley & Associates, Inc., (subject to compliance to HB1295).

BACKGROUND


Fiscal Impact

Attachments