CAPTION
Ratification of the fully executed Change Order No. 1 reflecting an increase in the amount of $32,061.22, and additional Ninety (90) construction calendar days, in connection with the Contract C-HCDD1-20-039-08-25 -"Mile 9 N & FM 1015 - Package 1A Improvements - 2018 Bond Referendum Project #24" with Mor-Wil, LLC as recommended by Project Engineer, Robert Saenz, PE, Halff Associates, Inc, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.