AI- 81785
Purchasing Department 26.B.3.
CC REGULAR AGENDA REGULAR MTG
Prct. 1
- Meeting Date:
- 07/27/2021
- Submitted For:
- Marty Salazar
- Submitted By:
- Hector Garcia, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
CAPTION
Acceptance and approval of Supplemental Agreement No. 2 for services under Work Authorization No. 1, Contract No. C-18-304-02-26 as submitted by the project engineer, L&G Engineering, to reallocate funds from Engineering Construction Management to Engineering Project Management in the amount of $119,861.00 in connection with the FM 88 Project.
BACKGROUND
It has become necessary to amend the following:
"Exhibit B - Scope of Services to be provided by the Engineer" to reflect the reallocation of funds from Engineering Construction Management to Engineering Project Management in the amount of $119,861.00.
"Exhibit D-1 - Estimated Man-hour Breakdown of Work Authorization No.1 to include costs associated with Project Management.
Estimated cost from the original Work Authorization No.1 will not increase or decrease the amount of $1,333,926.00.
"Exhibit B - Scope of Services to be provided by the Engineer" to reflect the reallocation of funds from Engineering Construction Management to Engineering Project Management in the amount of $119,861.00.
"Exhibit D-1 - Estimated Man-hour Breakdown of Work Authorization No.1 to include costs associated with Project Management.
Estimated cost from the original Work Authorization No.1 will not increase or decrease the amount of $1,333,926.00.
Fiscal Impact
- CALENDAR YEAR:
- 2021
- ACCT. #:
- 1-1353-431-00-121-259-0-841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
CO2018B-PCT1 FM88(5THAVE-FM1925)-AID GOV; PO #795177 for L & G Consulting Engineers, Inc; funds available as of 7-23-2021Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/23/2021 11:37 AM |
| Budget and Management | ngonzalez1 | 07/23/2021 01:59 PM |
| Final Approval | Monica Salinas | 07/24/2021 09:44 AM |
- Form Started By:
- Hector Garcia
- Started On:
- 07/21/2021 05:55 PM
- Final Approval Date:
- 07/24/2021