Presentation for consideration, discussion acceptance and approval of Change Order No 2 for "Las Haciendas Subdivision" C-CAP-07-023-08-07 adding 15 days to the original contract time with TRC Construction (with no fiscal impact) as submitted through project engineer R. Gutierrez Engineering Corporation, under Border Colonia Access Program Project(s).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
NO FISCAL IMPACTSubdivision project is currently being funded in conjunction with an interlocal agreement with the City of Pharr.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/07/2008 09:31 AM |
| Budget and Management | Dina Trevino | 03/07/2008 09:57 AM |
| Rey Salazar | Rey Salazar | 03/07/2008 03:17 PM |
| Auditor's Office | 03/07/2008 05:56 PM |
- Form Started By:
- lmoya
- Started On:
- 03/05/2008 03:19 PM
- Final Approval Date:
- 03/07/2008