Skip to main content

AgendaQuick™

View Agenda Item

AI - 83904
4.B.
DD-CONSENT AGENDA REGULAR MTG
Meeting Date:
12/28/2021
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

CAPTION

Ratification of the fully executed Change Order No. 2 reflecting Thirty-one (31) additional calendar days, in connection with Contract C-HCDD1-20-063-11-12, “P.S.J.A. Lateral Drain Ditch Improvements (Earling Road to South Main Drain Phase I)" with  Saenz Brothers Construction, LLC, and as recommended by Project Engineer, Javier Hinojosa Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM. 

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 12/22/2021 04:44 PM
Form Started By:
moysalazar
Started On:
12/17/2021 03:57 PM
Final Approval Date:
12/22/2021