AI- 84318
Purchasing Department 25.D.2.
CC REGULAR AGENDA SPECIAL MTG
Prct. 1
- Meeting Date:
- 04/19/2022
- Submitted For:
- Eduardo Belmarez
- Submitted By:
- Hector Garcia, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
CAPTION
Requesting approval of the following Change Order for Texas Cordia Construction, LLC [C-19-274-04-07], as recommended by the project engineer, SAMES, in connection to HC Precinct No.1-Mile 6 W Road Project (Mile 9 to Mile 11).
| Description | Total Amount |
| Change Order No.5 *Changes to contract time based on various circumstances outside the contractor's control. * Adds 4 months to the Quantity of Item [502-6001] Barricades, Signs and Traffics Handling for the corresponding traffic control. |
$19,600.00 |
BACKGROUND
The various items that impacted TCC's schedule included:
- MVEC Power Poles in the way of construction from Mile 9 N to Mile 10 N (27 days)
- MVEC Power Poles in the way of construction from Mile 10 N to Mile 11 N (12 days)
- MVEC Power Poles north of Mile 11 N (10 days)
- Mile 10 N Intersection Drill Shaft and Coordination with HCCID#9 (20 days)
Fiscal Impact
- CALENDAR YEAR:
- 2021
- ACCT. #:
- 1-1351-431-00-121-039-1-721
- FUNDS AVAILABLE Y/N?:
- N
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Interdepartmental Transfer for additional funding (AI-85484)Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | ebelmarez | 04/14/2022 02:26 PM |
| Budget and Management | Veronica Ortiz | 04/14/2022 03:32 PM |
| Final Approval | Monica Salinas | 04/15/2022 04:20 PM |
- Form Started By:
- Hector Garcia
- Started On:
- 01/20/2022 06:34 PM
- Final Approval Date:
- 04/15/2022