Information
CAPTION
Requesting approval of Change Order No. 5 reflecting an increase in the amount of $302,789.13, and Sixty (60) additional construction calendar days, in connection with Contract No. C-HCDD1-20-034-08-11 -"Jackson Road Drain Phase I -2018 Bond Referendum Project No. 16'' with RG Enterprises, LLC, dba G&G Contractors, as recommended by Project Engineer, Quintanilla, Headley & Associates.