CAPTION

Requesting approval of Supplemental Agreement No.2 to Work Authorization No. 3 of C-13-336-12-10, as submitted by the project engineer, L&G Engineering, It has become necessary to amend the "Exhibit D-1 Estimated Man-Hour Breakdown" for Work Authorization No.3 to reallocate funds from Construction Management to Project management.

BACKGROUND

C-13-336-12-10 it has become necessary to amend the Engineering Construction Management (32002) decrease ($132,300.00) Add Funds Engineering Project Management (FC 16403) $132,300.00 the Estimated Cost will transfer from Construction Management to Project Management, no increase or decrease from the original Work Authorization No. 2 in the amount of $1,621,317.06; therefore the amount of Supplemental No. 2 is 0.00 

Fiscal Impact

CALENDAR YEAR:
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No fiscal impact

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal ebelmarez 08/05/2022 09:56 AM
Budget and Management Veronica Ortiz 08/05/2022 11:14 AM
Purchasing / Internal ebelmarez 08/05/2022 02:15 PM
Budget and Management Veronica Ortiz 08/05/2022 02:29 PM
Final Approval Monica Salinas 08/13/2022 09:50 AM
Form Started By:
Victor Borrego
Started On:
08/03/2022 03:43 PM
Final Approval Date:
08/13/2022