CAPTION

A. Requesting approval of Change Order No. 5 to [C-20-294-02-23] with REIM Construction, Inc for Hidalgo County Precinct No. 3 - Mile 3 N. Road Project (Tom Gill Road to FM 492 [Goodwin Road]) [as detailed in document] and recommended by project engineer, B2Z Engineering and subject to receipt of TXDOT letter of concurrence.

BACKGROUND

Change Order #5 in the amount of $100,615.00 and 15 days has been reviewed and approved by Hidalgo County Precinct 3 to make the following contract changes. Change Order #5 adds to the original Mile 3 contract by 1) providing drainage to the north side of Mile 3 for Liberty Road, 2) redesigning the riprap slopes on the 1101ih and south sides of Mile 3 to match field conditions and minimize erosion, and 3) redesigning the sidewalks on the north and south side of Mile 3 to match the riprap slopes. CO #5 only uses existing items to increase or decrease quantities. Precinct #3 has reviewed and approved the modifications provided herein Change Order #5.

Fiscal Impact

CALENDAR YEAR:
2022
ACCT. #:
2-1315-431-00-123-051-0-841
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal ebelmarez 08/31/2022 06:28 PM
Budget and Management Veronica Ortiz 09/01/2022 12:02 PM
Final Approval Monica Salinas 09/02/2022 05:55 PM
Form Started By:
Victor Borrego
Started On:
08/23/2022 11:57 AM
Final Approval Date:
09/02/2022