AI- 88416
Purchasing Department 23.F.1.
CC REGULAR AGENDA SPECIAL MTG
Prct. 4
- Meeting Date:
- 11/15/2022
- Submitted By:
- Letty Saenz, COMM. PCT. #4
- Department:
- COMM. PCT. #4
CAPTION
Requesting approval of Change Order No. 1 as recommended by project architect to increase for an additional (45-days) in connection to Agreement #C-21-228-02-11 with RG Enterprises, LLC dba G & G Contractors for ongoing project: "Construction of All-Star Park" in Precinct 4, subject to compliance with Form 1295.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2022
- ACCT. #:
- 2-1286-452-20-124-229-1-740/730
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Acct#s 2-1286-452-20-124-229-1-740/730Attachments