AI- 88953
Purchasing Department 14.C.2.
CC REGULAR AGENDA SPECIAL MTG
Prct. 2
- Meeting Date:
- 01/03/2023
- Submitted For:
- Eddie Cantu
- Submitted By:
- Lupita Garza, COMM. PCT. #2
- Department:
- COMM. PCT. #2
CAPTION
Requesting approval of the following items for the Pct 2 Dicker Road (23rd - Jackson Rd) Project as submitted by the contractor, 2GS, LLC and as reviewed by project inspector, Saul Munoz, P.E. through contract #C-19-017-11-05:
A. Acceptance of the Certificate of Substantial Completion, reflecting the date of March 9, 2022.
B. Acceptance of the Certificate of Construction Completion, reflecting the date of September 23, 2022.
A. Acceptance of the Certificate of Substantial Completion, reflecting the date of March 9, 2022.
B. Acceptance of the Certificate of Construction Completion, reflecting the date of September 23, 2022.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2022
- ACCT. #:
- 2-1315-431-00-122-062-0-721
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
TXDOT-PCT2 DICKER RD(23RD-JACKSON)-ROADS; no fiscal impact.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | ebelmarez | 12/27/2022 03:05 PM |
| Budget and Management | Damiana Molina | 12/27/2022 03:14 PM |
| Final Approval | Monica Salinas | 12/29/2022 02:49 PM |
- Form Started By:
- Lupita Garza
- Started On:
- 12/20/2022 01:15 PM
- Final Approval Date:
- 12/29/2022