AI - 89224
6.F.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 01/17/2023
- Submitted By:
- Alvaro Chuc, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
South I Road Drain (East Side) - Budget 533
1. Approval of Application for Payment No. 3 in the amount of $35,540.14 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-029A-08-09. Project Engineer: B2Z Engineering PO#646597
2. Approval of Application for Payment No. 4 in the amount of $52,419.42 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-029A-08-09. Project Engineer: B2Z Engineering PO#646597
1. Approval of Application for Payment No. 3 in the amount of $35,540.14 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-029A-08-09. Project Engineer: B2Z Engineering PO#646597
2. Approval of Application for Payment No. 4 in the amount of $52,419.42 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-029A-08-09. Project Engineer: B2Z Engineering PO#646597
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 01/13/2023 04:57 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 01/13/2023 08:25 AM
- Final Approval Date:
- 01/13/2023