Ratification of approved and fully executed Change Order No. 1, in connection with the project "East Mercedes Drainage Improvements, 2018 Bond Referendum Project 10B’’, reflecting an increase of $39,341.70 and Twenty (20) additional Construction Calendar Days to Contract No. C-HCDD1-22-051-01-17, with RBM Contractors, LLC, as recommended by Project Engineer, Yvette Barrera, PE, CFM, Asst. District General Manager.
BACKGROUND
Project completion date: September 22, 2023
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 06/26/2023 04:28 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 06/26/2023 01:29 PM
- Final Approval Date:
- 06/26/2023