Information

CAPTION

Ratification of approved and fully executed Change Order No. 1, reflecting fifty-one (51) additional construction calendar days, in connection with the project "Re-Construction of Main Floodwater Channel Weir No. 4’', Contract No. (C-HCDD1-22-030-07-12), with Clore Equipment, LLC, as recommended by Project Engineer, International Consulting Engineers (ICE).

BACKGROUND

Project completion date as per CO1: August 27, 2023