AI- 91918
Purchasing Department 12.C.2.
CC CONSENT AGENDA SPECIAL MTG
Prct. 2
- Meeting Date:
- 08/08/2023
- Submitted For:
- Eddie Cantu
- Submitted By:
- Lupita Garza
- Department:
- COMM. PCT. #2
Information
CAPTION
Approval of Application for Payment No. 7 in the amount of $221,268.34 for Pct 2 Las Milpas Road Project submitted by the contractor, George Olivares, dba Go Underground, LLC (Contract C-22-0094-09-06) and reviewed by the project engineer, Saul R. Munoz, P.E.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2023
- ACCT. #:
- 3-1XXX-431-X0-1XX-XXX-X-XXX
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
PO #856776 for George Olivares d/b/a Go Underground, LLC; funds available as of 08-03-2023.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 08/03/2023 01:25 PM |
| Budget and Management | Damiana Molina | 08/03/2023 03:07 PM |
| Final Approval | Margaret Mungia | 08/04/2023 06:46 PM |
- Form Started By:
- Lupita Garza
- Started On:
- 08/03/2023 08:08 AM
- Final Approval Date:
- 08/04/2023