“Subject to Compliance with HB 1295” the Urban County Program is requesting consideration and action to award and enter into a construction contract with Saenz Brothers Construction, the lowest responsible bidder in the amount of $4,622,261.50 utilizing funds awarded to Hidalgo County by the Texas General Land Office (GLO) under Contract No. 22-082-005-D200 for the 2016 State Mitigation Competition Phase 2 Segment D project.
BACKGROUND
The bid opening was held on August 16, 2023 and the lowest responsible bidder meeting all specifications and/or requirements was Saenz Brothers Construction. Contract includes the award of Base Bid, Alternate #2 and Alternate #3. This GLO project is entitled the Hidalgo County Main Floodwater Channel Expansion – Phase 2 Segment D. Please see attached letter of recommendation by HCDD#1, project engineers and contractor’s general liability insurance.
Contractor: Saenz Brothers Construction
Contract Amount: $4,622,261.50
Available Funds: $9,962,444.40 GLO Construction Budget funds (Contract No. 22-082-005-D200
Contractor: Saenz Brothers Construction
Contract Amount: $4,622,261.50
Available Funds: $9,962,444.40 GLO Construction Budget funds (Contract No. 22-082-005-D200
Fiscal Impact
Attachments
- 1295
- w-9 forms
- Construction contract
- engineers letter
- Financial Report
- Bid Tabulation form
- Debarment
- ERR
- Insurance
- DA Approval
- Authority to use funds
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 08/29/2023 11:14 AM |
| Final Approval | Monica Salinas | 09/01/2023 04:05 PM |
- Form Started By:
- Michelle Garza
- Started On:
- 08/29/2023 10:47 AM
- Final Approval Date:
- 09/01/2023