AI - 92718
3.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 10/03/2023
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 1, for the project "South Lateral Drain Improvements Phase I'', reflecting an increase of thirty-five (35) additional construction calendar days to Contract No. C-HCDD1-20-009-R-04-04, with Saenz Brothers Construction, LLC., as recommended by Project Engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Project completion date as per CO-1: September 7, 2023
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/29/2023 04:09 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 09/29/2023 10:21 AM
- Final Approval Date:
- 09/29/2023