CAPTION
Rincon de Encinos Phase 3 - Budget 010
1. Approval of Application for Payment No. 1 in the amount of $124,801.76 from McAllen Multi Service pertaining to Construction Contract C-HCDD1-23-033-08-08 Rincon de Encinos Phase III. Project Engineer: HCDD1 Omar Anzaldua, Jr. PE, PO#648190
Highway 281 & FM 88 - Budget 514
2. Approval of Application for Payment No. 8 in the amount of $66,960.00 from Go Underground pertaining to Construction Contract C-HCDD1-22-019-004-20 Highway 281 & FM 88. Project Engineer: Cruz Hogan, PO#646340
South Lateral Drain Structure - Budget 534
3. Approval of Application for Payment No. 2 in the amount of $201,249.23 from Saenz Brothers Construction pertaining to Construction Contract C-HCDD1-20-009-R-04-04 South Lateral Drain Structure. Project Engineer: HCDD1 Omar Anzaldua, Jr. PE, PO#647846
1. Approval of Application for Payment No. 1 in the amount of $124,801.76 from McAllen Multi Service pertaining to Construction Contract C-HCDD1-23-033-08-08 Rincon de Encinos Phase III. Project Engineer: HCDD1 Omar Anzaldua, Jr. PE, PO#648190
Highway 281 & FM 88 - Budget 514
2. Approval of Application for Payment No. 8 in the amount of $66,960.00 from Go Underground pertaining to Construction Contract C-HCDD1-22-019-004-20 Highway 281 & FM 88. Project Engineer: Cruz Hogan, PO#646340
South Lateral Drain Structure - Budget 534
3. Approval of Application for Payment No. 2 in the amount of $201,249.23 from Saenz Brothers Construction pertaining to Construction Contract C-HCDD1-20-009-R-04-04 South Lateral Drain Structure. Project Engineer: HCDD1 Omar Anzaldua, Jr. PE, PO#647846
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/29/2023 04:27 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 09/29/2023 02:18 PM
- Final Approval Date:
- 09/29/2023