AI - 93072
7.A.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 10/31/2023
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 2 reflecting an increase in the amount of $119,907.12 and additional 40 construction calendar days for ''South Lateral Drain -IBWC No. 23AL -2018 Bond Referendum Project No. 34''; (C-HCDD1-22-033-07-12) with Mor Wil, LLC., as recommended by Project Engineer, Yvette Barrera, P.E., CFM.
BACKGROUND
Completion date as per Ch Ord. 2: February 4, 2024