CAPTION

Ratification of approved and fully executed Change Order No. 2, reflecting fifty (50) additional construction calendar days, and an increase in the amount of $28,938.03 in connection the project ''Re-Construction of Main Floodwater Channel Weir No. 4’'; Contract No. C-HCDD1-22-030-07-12, with Clore Equipment, LLC, as recommended by Project Engineer, International Consulting Engineers (ICE).

BACKGROUND

1. Concrete Rip Rap - Additional 33 CY needed  with a total of  104 CY (33CY + 71 CY), per Bid Item #3
2. Fifty (50) additional construction days (5 weather days, 20 for additional grading Rip Rap & 25 dewatering days)

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 11/09/2023 04:21 PM
Form Started By:
Enriqueta Zambrano
Started On:
11/07/2023 01:41 PM
Final Approval Date:
11/09/2023