AI - 93183
3.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 11/14/2023
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 2, reflecting fifty (50) additional construction calendar days, and an increase in the amount of $28,938.03 in connection the project ''Re-Construction of Main Floodwater Channel Weir No. 4’'; Contract No. C-HCDD1-22-030-07-12, with Clore Equipment, LLC, as recommended by Project Engineer, International Consulting Engineers (ICE).
BACKGROUND
1. Concrete Rip Rap - Additional 33 CY needed with a total of 104 CY (33CY + 71 CY), per Bid Item #3
2. Fifty (50) additional construction days (5 weather days, 20 for additional grading Rip Rap & 25 dewatering days)
2. Fifty (50) additional construction days (5 weather days, 20 for additional grading Rip Rap & 25 dewatering days)
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/09/2023 04:21 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 11/07/2023 01:41 PM
- Final Approval Date:
- 11/09/2023