AI- 93233
Planning Department 5.D.
CC CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 11/14/2023
- Submitted For:
- Flor Castillo
- Submitted By:
- Flor Castillo
- Department:
- PLANNING DEPT.
Information
CAPTION
1. PIPELINE AND UTILITY PERMITS
a. Applicant: North Alamo Water Supply Corporation
Legal Description: Lot 13 Blk. 102 Turner Tract Subdivision (Mile 22 ½ North Road & F.M. 491) (Pct. 1)
Location of Pipeline or Utilities: Existing 2” waterline south of Mile 22 ½ North Road.
Proposed improvement within Right-of-Way: One 3/4” water service line with a 2” PVC casing boring Mile 22 ½ North Road.
b. Applicant: North Alamo Water Supply Corporation
Legal Description: 18.806 acres out of the south ½ of lot 6 section 249 Tex-Mex Railway Co. Survey; Proposed, Jaguar Heights Subdivision (Terry Road & Mile 17 North Road) (Pct. 4)
Location of Pipeline or Utilities: Existing 12” waterline south of Mile 17 North Road.
Proposed improvement within Right-of-Way: Two 8” water line with a 16” PVC casing boring Mile 17 North Road.
c. Applicant: Spectrum (Project No. 1811905-EM17E)
Proposed location of Power Supply Pole:North of Cactus Lane approximately 130.00 feet west of Seminary Road. (Pct. 4)
d. Applicant: Spectrum (Project No. 1819015-EM16E)
Proposed location of Power Supply Pole:North of Siguena Drive approximately 900.00 feet west of Seminary Road. (Pct. 4)
a. Applicant: North Alamo Water Supply Corporation
Legal Description: Lot 13 Blk. 102 Turner Tract Subdivision (Mile 22 ½ North Road & F.M. 491) (Pct. 1)
Location of Pipeline or Utilities: Existing 2” waterline south of Mile 22 ½ North Road.
Proposed improvement within Right-of-Way: One 3/4” water service line with a 2” PVC casing boring Mile 22 ½ North Road.
b. Applicant: North Alamo Water Supply Corporation
Legal Description: 18.806 acres out of the south ½ of lot 6 section 249 Tex-Mex Railway Co. Survey; Proposed, Jaguar Heights Subdivision (Terry Road & Mile 17 North Road) (Pct. 4)
Location of Pipeline or Utilities: Existing 12” waterline south of Mile 17 North Road.
Proposed improvement within Right-of-Way: Two 8” water line with a 16” PVC casing boring Mile 17 North Road.
c. Applicant: Spectrum (Project No. 1811905-EM17E)
Proposed location of Power Supply Pole:North of Cactus Lane approximately 130.00 feet west of Seminary Road. (Pct. 4)
d. Applicant: Spectrum (Project No. 1819015-EM16E)
Proposed location of Power Supply Pole:North of Siguena Drive approximately 900.00 feet west of Seminary Road. (Pct. 4)
BACKGROUND
Fiscal Impact
Attachments
- 1 GLADIS ZUNIGA (NAWSC)
- 2 - JAGUAR HEIGHTS SUB (NAWSC)
- 3 - Spectrum 1811905-EM17E
- 4 - Spectrum 1819015-EM16E
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Damiana Molina | 11/09/2023 10:05 AM |
| Final Approval | Monica Salinas | 11/09/2023 05:20 PM |
- Form Started By:
- Flor Castillo
- Started On:
- 11/08/2023 04:30 PM
- Final Approval Date:
- 11/09/2023