CAPTION
Ratification of approved and fully executed Change Order No.4, in connection with the project "Mission-McAllen Rado Phase I -2018 Bond Referendum Project No. 25’', reflecting an increase of two-hundred and five (205) additional construction calendar days to Contract No. C-HCDD1-21-023-07-27, with Gonzalez Engineering & Management, LLC, as recommended by Project Engineer, B2Z Engineering, LLC.
BACKGROUND
Project completion date for this change order: February 19, 2024