Ratification of approved and fully executed Change Order No. 3, reflecting twenty-six  (26) additional construction calendar days, in connection with the project ''Re-Construction of Main Floodwater Channel Weir No. 4’'; Contract No. C-HCDD1-22-030-07-12, with Clore Equipment, LLC, as recommended by Project Engineer, International Consulting Engineers (ICE).

BACKGROUND

Completion date for this Change Order: November 11, 2023