AI - 93911
4.A.
DD-CONSENT AGENDA REGULAR MTG
Meeting Date:
01/23/2024
Submitted For:
Yvette Barrera
Submitted By:
Enriqueta Zambrano
Department:
DRAINAGE DISTRICT

CAPTION

Ratification of approved and fully executed Change Order No.1, in connection with the project "South ''I'' Rd USIBWC Structure 82L -2018 Bond Referendum Project No. 33’', reflecting an increase in the amount of $14,900.00 and additional 20 construction calendar days to Contract No. C-HCDD1-22-060-11-29, with Mor-Wil, LLC, as recommended by Project Engineer, B2Z Engineering.

BACKGROUND

Project completion date: May 17, 2024, per change order 1

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 01/19/2024 04:19 PM
Form Started By:
Enriqueta Zambrano
Started On:
01/12/2024 04:00 PM
Final Approval Date:
01/19/2024