AI - 93911
4.A.
DD-CONSENT AGENDA REGULAR MTG
- Meeting Date:
- 01/23/2024
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of approved and fully executed Change Order No.1, in connection with the project "South ''I'' Rd USIBWC Structure 82L -2018 Bond Referendum Project No. 33’', reflecting an increase in the amount of $14,900.00 and additional 20 construction calendar days to Contract No. C-HCDD1-22-060-11-29, with Mor-Wil, LLC, as recommended by Project Engineer, B2Z Engineering.
BACKGROUND
Project completion date: May 17, 2024, per change order 1
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 01/19/2024 04:19 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 01/12/2024 04:00 PM
- Final Approval Date:
- 01/19/2024