AI - 94430
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 03/05/2024
- Submitted For:
- Jaime Salazar
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the approved and fully executed Change Order No. 2, reflecting an additional 181 calendar days for the project "Highway 281 & FM 88 - 2018 Bond Referendum Project #14", (C-HCDD1-22-019-07-12), with Go Underground, LLC., as recommended by Project Engineer, Cruz-Hogan Consultants, Inc. and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
New end date as per CO2: 03/20/2024
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/01/2024 04:28 PM |
- Form Started By:
- Justin Silva
- Started On:
- 02/28/2024 02:00 PM
- Final Approval Date:
- 03/01/2024