Purchasing Department   11.F.2.
CC CONSENT AGENDA SPECIAL MTG
Prct. 4
Meeting Date:
09/03/2024
Submitted For:
Ignacio Amezcua
Submitted By:
Juan Herrera
Department:
PURCHASING DEPT.

Information

CAPTION

A. Requesting acceptance and approval of Change Order No. 3 from RDH Site and Concrete, LLC, for the Hidalgo County Precinct 4 "[ARPA-22-124-049] - Construction for Mile 17 Rd Stormwater Project" (C-22-0087-08-22-10), for a 21-day extension and a total project amount decrease of $22,085.00, as recommended by the Project Engineer, L&G Consulting Engineers, Inc. 
B. Requesting approval of the Certificate of Substantial Completion for the Hidalgo County Precinct 4 "[ARPA-22-124-049] - Construction for Mile 17 Rd. Stormwater Project" (C-22-0087-08-22-10), as recommended by the Project Engineer, Hidalgo County Drainage District No.1

BACKGROUND

Project No: 22-0087-08-10-22

Fiscal Impact

CALENDAR YEAR:
2024
ACCT. #:
4-1290-431-50-115-242-4-723
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Ignacio Amezcua 08/30/2024 05:58 PM
Final Approval Monica Salinas 08/30/2024 06:17 PM
Form Started By:
Juan Herrera
Started On:
08/28/2024 02:13 PM
Final Approval Date:
08/30/2024