AI- 97385
Purchasing Department 11.B.1.
CC CONSENT AGENDA SPECIAL MTG
Prct. 1
- Meeting Date:
- 11/12/2024
- Submitted For:
- Ignacio Amezcua
- Submitted By:
- Janie Moron
- Department:
- PURCHASING DEPT.
Information
CAPTION
A. Requesting approval of Supplemental Agreement No. 1 to Work Authorization No. 1 for the "Sunset Hill Park Pavilion Project" to include sub-consultant MEP Engineering services in the amount of $9,000.00
B. Pursuant to Article 14 of the agreement (C-22-0013-03-08), requesting authority for Chanin Engineering, LLC to engage subcontractor Trinity MEP Engineering, LLC.
B. Pursuant to Article 14 of the agreement (C-22-0013-03-08), requesting authority for Chanin Engineering, LLC to engage subcontractor Trinity MEP Engineering, LLC.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2024
- ACCT. #:
- 4-1303-452-00-121-286-0-740
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 11/08/2024 05:19 PM |
- Form Started By:
- Janie Moron
- Started On:
- 11/08/2024 10:29 AM
- Final Approval Date:
- 11/08/2024