Information

CAPTION

Requesting approval of Change Order No.1, reflecting an increase in the amount of $88,464.50 and 60 additional construction calendar days for the project ''Pharr-McAllen Lateral East - 2023 Bond Referendum Project No. 9'', Contract No. C-HCDD1-24-029-06-11, with Synergy Development & Construction, LLC, as recommended by Project Engineer, GDJ Engineering LLC.

BACKGROUND

1.     To install 5" Concrete Rip-Rap on the North side of the existing ditch to prevent erosion at the outfall. 
2.     Additional 60 days to complete the Rip-Rap 
3.    Project end date for this change order: April 29, 2025

At the request of the Hidalgo County Drainage District No. 1

Fiscal Impact

CALENDAR YEAR:
2025
ACCOUNT #:
25-173-433-709-47330-020-301
FUNDS AVAILABLE? Y/N:
Y
MATCHING FUNDS? Y/N:

BUDGETARY IMPACT:

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 02/28/2025 04:35 PM
Form Started By:
Enriqueta Zambrano
Started On:
02/27/2025 01:46 PM
Final Approval Date:
02/28/2025