CAPTION
Ratification of approved and fully executed Change Order No.3, reflecting a decrease in the amount ($22,145.64) and additional 60 construction calendar days for the project ''Mile 10 N. & Baseline Rd Phase II -USIBWC Structure 139 -2018 Bond Referendum Project No. 20'', Contract No. C-HCDD1-23-014-06-13, with RBM Contractors, LLC, as recommended by Project Engineer, Quintanilla, Headley & Associates and approved by Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Contract end date as per change order 3: 7/29/2025