CAPTION

Requesting approval of Construction Change Order No.6 increase in the amount of $4,025.00 with Mission Paving Company, Inc. (contracted vendor for "Tower road Phase I Project") reflecting the items described on change order, with authority for County Judge or Court Member to execute document.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1200-431-00-122-049-0-731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO #662859 available balance of $148,480.90 as of 3/21/2012