Urban County Program for Hidalgo County Precinct No. 4 is requesting consideration and action to award and enter into construction contract with The 5125 Company for base bid, Alternate No.’s 1-7 and 9. Total amount of contract is $427,144.45 for a HUD CDBG-R Fike Pump Structure utilizing FY 22 (2009) CDBG-R flood drainage improvements and FY 23 (2010) flood drainage improvements.
BACKGROUND
Saenz Utility Contractors, Ltd. formally rejected their bid on April 10, 2012. After review of bid tabulations, Raul Sesin P.E., C.F.M. recommended that the base bid and alternates 1-7 and 9 is to be completed by The 5125 Company as the lowest of three (3) bidders. (See attached recommendation letter from the Raul Sesin, P.E., C.F.M. and copy of the bid tabulation.)
Contractor The 5125 Company
Contract Amounts: $427,144.45
Funds Available: $250,440.08 Year 22 (2009) CDBG-R Precinct No. 4 – Flood Drainage Improvements
Precinct No. 4 funds : $278,234.44 Year 23 (2010) Precinct No. 4 – Flood Drainage Improvements
Total: $528,674.52
Contractor The 5125 Company
Contract Amounts: $427,144.45
Funds Available: $250,440.08 Year 22 (2009) CDBG-R Precinct No. 4 – Flood Drainage Improvements
Precinct No. 4 funds : $278,234.44 Year 23 (2010) Precinct No. 4 – Flood Drainage Improvements
Total: $528,674.52
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 05/23/2012 04:31 PM |
| Purchasing / Internal | Monica Salinas | 06/01/2012 05:02 PM |
- Form Started By:
- Melissa Flores
- Started On:
- 05/23/2012 11:47 AM
- Final Approval Date:
- 06/01/2012