Acceptance, and approval of the following items for C-CAP-12-115-06-12 Esperanza Estates Subdivision between Hidalgo County and 2GS, LLC as submitted through project engineer DOS Logistics, Inc.:

a. Final construction contract (CC awarded 06-12-12) in the amount of $80,125.00;

b. Pursuant to TXLGC 262.031 and in the interest of expediting a project's progress, requesting authority/approval for the Precinct Commissioner or designee to execute change orders that involve ...'an increase or decrease in cost of $50,000.00 or LESS...'.  The original contract price may not be decreased by 18 % or more without the consent of the contractor".

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1200-431-00-122-262-0-731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

$86,044.06 available balance as of 08/23/12.