CAPTION
Acceptance and approval of the final construction contract documents (awarded by CC-09-25-12) with STFC, Inc. dba Fresno Construction in the approved amount of $188,710.75 for: "Hidalgo County Precinct No. 4 -Construction of a New Multi Purpose Facility and Mechanical Shop -Civil Site Improvements (C-12-056C-09-25)."
BACKGROUND
Project Purchase Order Requisition No. 224705.
Fiscal Impact
- FISCAL YEAR:
- 2012
- ACCT. #:
- 2-1342-431-00-124-07X-0-720
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available balance as of 10-12-12:Program# Amount
075 $1,002,273.40
078 $ 61,463.85
079 $ 12,083.00
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/12/2012 01:28 PM |
| Budget and Management | mmunoz | 10/12/2012 01:30 PM |
| Auditor's Office | Alejandro Garcia | 10/12/2012 05:08 PM |
- Form Started By:
- moysalazar
- Started On:
- 10/12/2012
- Final Approval Date:
- 10/12/2012