a. Presentation for discussion, acceptance and approval of the conceptual layout of the, "New Commissioners' Court Room Facility," as developed by the project architect, Alcocer Garcia Associates, Inc. from directions proposed by Executive Officer for CC and, if approved; 

b. Authority for project archiect, AGA to proceed with the Design Development Phase for the addition to the former administration building project (100 E. Cano, Edinburg) titled the design and construction of a New Commissioners' Court Room Chamber Facility.

BACKGROUND

CC approved the Amendment #2 to the AIA B-141-1997 Standard Form of Agreement with Alcocer Garcia Associates, Inc. on 10-23-12, AI #34853,item 17.A.4.  

Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1342-419-40-220-043-0-452
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available as of 11-16-12. Additional estimated construction cost is $1.2M, as provided by project architect, AGA.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/16/2012 11:19 AM
Budget and Management mmunoz 11/16/2012 11:39 AM
Auditor's Office Alejandro Garcia 11/16/2012 05:13 PM
Form Started By:
Rocio Villarreal
Started On:
11/15/2012 03:10 PM
Final Approval Date:
11/16/2012