Information
CAPTION
Urban County Program, on behalf of the Hidalgo County Precinct No. 2, is requesting approval of a best and final negotiated contract for construction material testing services with Raba Kistner in the amount of $48,834.23 utilizing General Land office (GLO) funds for South Fork Drain project in Pharr, Texas.
BACKGROUND
Raba Kistner has submitted a best and final offer for the required construction material testing
Services for the South Fork Drain project which consists of geotechnical and construction material testing services. Raba Kistner was the highest ranked firm by Commissioner’s Court on February 11, 2014. See attached contract, letter of best and final offer, scope of services, and certificate of liability insurance.
Geo-Tech Firm: Raba Kistner
Contract Amount: $48,834.23
Funds Available: $424,157.00 6540-61-0309-5100-6100 Engineering Funds
Services for the South Fork Drain project which consists of geotechnical and construction material testing services. Raba Kistner was the highest ranked firm by Commissioner’s Court on February 11, 2014. See attached contract, letter of best and final offer, scope of services, and certificate of liability insurance.
Geo-Tech Firm: Raba Kistner
Contract Amount: $48,834.23
Funds Available: $424,157.00 6540-61-0309-5100-6100 Engineering Funds
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 02/26/2014 02:23 PM |
| Purchasing / Internal | Monica Salinas | 03/07/2014 05:22 PM |
- Form Started By:
- Melissa Flores
- Started On:
- 02/26/2014 01:29 PM
- Final Approval Date:
- 03/07/2014