CAPTION

a. Requesting approval of  Construction Change Directive No. 2 ($73,651.00-includes item 1,2,3 &4 re-designs for CC chambers to include Public Affairs & County Judge's suites to add Emergency Mgmt plus Vaults) in connection with the "Repairs and Renovations-1st and 2nd Floors to the Former Administration Building" from contracted vendor, D. Wilson Construction Company, and as recommended by project architect, Alcocer Garcia Associates with authority for County Judge or Court member to execute document;
 
b. Requesting approval of Change Order No. 1 (increase-reflects CCD #s 1 & 2) in connection with the "Repairs and Renovations-1st and 2nd Floor to the Former Administration Building," in the amount of $81,802.00 from contracted vendor, D. Wilson Construction, Inc., and as recommended by project architect, Alcocer Garcia Associates, with authority for County Judge to execute document.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2014
ACCT. #:
4-1336-419-40-220-043-0-452
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available as of 3/7/14.
PO#698457
Proposed cost of an additional $81,802.00 to the existing PO.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 03/07/2014 10:08 AM
Budget and Management Debbie Tamez 03/07/2014 10:21 AM
Auditor's Office Monica Salinas 03/07/2014 05:22 PM
Form Started By:
Rocio Villarreal
Started On:
02/26/2014 04:52 PM
Final Approval Date:
03/07/2014