8.
DRAINAGE DISTRICT
- Meeting Date:
- 03/11/2014
- Submitted By:
- Sylvia Sanchez, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
2013 Bond Series
Request Approval of Pay Estimate No. 2 to IRP South Central, LLC for the Construction of the RADO Storm Rehab project i the amount of $491,207.76. Contract approved 11-12-13.
Request Approval of Pay Estimate No. 2 to IRP South Central, LLC for the Construction of the RADO Storm Rehab project i the amount of $491,207.76. Contract approved 11-12-13.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 02/26/2014 04:05 PM |
| Final Approval | Monica Salinas | 03/07/2014 05:20 PM |
- Form Started By:
- ssanchez
- Started On:
- 02/26/2014 03:26 PM
- Final Approval Date:
- 03/07/2014