Approval of Construction Change Directive #4 (as drafted/submitted through project architect, Alcocer/Garcia & reviewed/concurred by construction manager, Prodigy) to change all interior hollow metal frames to frameworks frames in an amount not to exceed $3,575.00 (without impact on quality or function) so as to give general contractor, D. Wilson Construction the notice to proceed to order.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1342-419-40-220-043-0-452
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funds available through PO# 698457, NO CHANGE IN CONTRACT SUM.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/21/2014 03:35 PM |
| Budget and Management | Debbie Tamez | 03/21/2014 03:36 PM |
| Auditor's Office | Monica Salinas | 03/21/2014 04:47 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 03/21/2014 01:43 PM
- Final Approval Date:
- 03/21/2014