CAPTION
a. Requesting approval of Change Order No. 1 (increase) in connection: "Repairs and Renovations-1st and 2nd Floor to the Former Administration Building," in the amount of $128,787.00 to awarded general contractor, D. Wilson Construction, Inc., and as recommended by project architect, Alcocer Garcia Associates with concurrence by construction manager, Prodigy, including authority for County Judge to execute document;
b. Acceptance and approval of an Amendment No. 2 to the AIA A101-2007 Standard Form of Agreement with D. Wilson Construction Company, for the "Remodel of Existing Old Administration Building (1st and 2nd Floor)," to remove the allowance schedules and re-direct to Betterment Allowance;
c. Requesting approval of clarifications to the following Construction Change Directives:
1. Change Directive No. 1 (approved CC 11/26/13) to be funded by allowance;
2. Change Directive No. 2 (CC 3/11/14-NOT APPROVED) thus null and void;
3. Change Directive No. 3 (CC 3/18/14) to be funded by either the allowances or Betterment Allowance;
d. Approval of Construction Change Directive #5 (as drafted/submitted through project architect, Alcocer/Garcia & reviewed/concurred by construction manager, Prodigy) for the access control in an amount $1,025.00.
b. Acceptance and approval of an Amendment No. 2 to the AIA A101-2007 Standard Form of Agreement with D. Wilson Construction Company, for the "Remodel of Existing Old Administration Building (1st and 2nd Floor)," to remove the allowance schedules and re-direct to Betterment Allowance;
c. Requesting approval of clarifications to the following Construction Change Directives:
1. Change Directive No. 1 (approved CC 11/26/13) to be funded by allowance;
2. Change Directive No. 2 (CC 3/11/14-NOT APPROVED) thus null and void;
3. Change Directive No. 3 (CC 3/18/14) to be funded by either the allowances or Betterment Allowance;
d. Approval of Construction Change Directive #5 (as drafted/submitted through project architect, Alcocer/Garcia & reviewed/concurred by construction manager, Prodigy) for the access control in an amount $1,025.00.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1336-419-40-220-043-0-452
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO 698457A PO increase will be attached by no later than Monday 3/31.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/28/2014 03:22 PM |
| Budget and Management | Debbie Tamez | 03/28/2014 03:23 PM |
| Auditor's Office | Monica Salinas | 03/28/2014 04:13 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 03/27/2014 12:48 PM
- Final Approval Date:
- 03/28/2014